Write a change request

Plan a real change, such as a router firmware update, through a proper change management process: impact analysis, test plan, backout plan and maintenance window.

Environment

A document or spreadsheet.

Before you start

  • Read Change Management Programs (p.385), Change Management Concepts (p.386) and Restarts, Dependencies, and Downtime (p.388).

You will

  • Complete a change request
  • Identify dependencies and downtime
  • Write a backout plan

Steps

  1. 1

    Pick a change: updating your router firmware, or upgrading your laptop's operating system.

  2. 2

    Fill in: requester, owner, description, reason, and change type (standard, normal or emergency).

  3. 3

    Impact analysis: which devices, services and people are affected, and for how long? What depends on this device?

  4. 4

    Test plan: how will you confirm it worked (internet access, Wi-Fi settings kept, VPN still working)?

  5. 5

    Backout plan: how you'll roll back if it fails (keep the old firmware file, export the current configuration first).

  6. 6

    Choose a maintenance window when nobody needs the network, and note who must approve.

  7. 7

    After the change, update your documentation and inventory, as in the version control section on p.390.

Check your understanding

  • ?Why is a backout plan required before approval rather than after a failure?
  • ?Which changes might be 'standard' (pre-approved)?
  • ?What documentation should you update afterwards?